No long road closures, detours during 2 resurfacing projects Published Oct. 17, 2014 By Contributed story WRIGHT-PATTERSON AIR FORCE BASE, Ohio -- Starting on Oct. 20, resurfacing work will begin on two roadways on base. The first location is near the Wright-Patterson Medical Center in Area A and will include parts of Schlatter, Talbot and Estabrook roads. The project will include resurfacing the roadway and replacing deteriorated curb and is scheduled for completion Nov. 7. The other location is C Street in Area B from Loop Road to Fifth Street. This project includes resurfacing the roadway along with replacing sunken storm inlets. The work is scheduled to be complete on Nov. 14. Refer to the maps for information on the project locations. There will be no long-term road closures or detours, but there may be short-term lane closures for the safety of the construction crew and motorists. Flaggers will be present to safely move traffic around the paving crews. Please use caution while driving in the work zones.